Recovery Assessment Worksheet

MechanicalElectricalRecovery

Executive Overview

The Recovery Assessment Worksheet consolidates electrical and mechanical findings into a single, defensible recovery-level determination — the point where inspection and testing results become an actual engineering decision.

Purpose

Individual test results (an IR/PI trend, a bearing inspection finding) don't by themselves tell you which of the four recovery levels applies. This worksheet exists to combine them systematically, following the same 4-level framework established in the flagship Handbook article.

When to Use

Classification

Engineering Discipline
Mechanical, Electrical
Machine Types
Motor, Generator, Pump
Industries
All — general-purpose

Required Inputs

Expected Outputs

A recommended recovery level (1-4) with the supporting evidence stated explicitly — the input needed for a cost estimate via the Recovery Scope Estimator.

The Worksheet

Recovery Assessment Worksheet
EvidenceFindingPoints Toward
IR/PI trend
Bearing / mechanical condition
Frame / core condition
Contamination extent
Indicated Recovery Level →[Level 1–4, or Replace]

Procedure

  1. Transfer the IR/PI trend conclusion from the Megger Test Record.
  2. Transfer mechanical/bearing findings from the Inspection Checklist.
  3. Assess frame and core condition (visual/structural).
  4. Cross-reference all findings against the 4-level framework: Level 1 (clean/dry/retest), Level 2 (component replacement), Level 3 (rewind), Level 4 (replace).
  5. State the indicated level with the evidence that supports it — never the level alone without its basis.

Acceptance Criteria

RecommendationA completed worksheet is acceptance-ready when every row has a finding (not left blank) and the indicated level is traceable to specific evidence above it — not asserted independently of the table.

Engineering Notes

Note
Electrical and mechanical evidence can point to different levels — when they conflict, the higher (more conservative) level generally governs, since either failure mode alone is sufficient to compromise the machine.

Typical Mistakes

Common Mistake
Determining the recovery level before all inputs are complete, then working backward to justify it — the worksheet should be filled top-to-bottom, not conclusion-first.

Related Content

Related Standards
ISO 20816 →IEEE 43 →
Related Knowledge Package
Flood-Damaged Electric Motor →

Future Download Formats

📄 PDF (planned)📊 Excel (planned)

The web version above is fully usable today. Downloadable formats follow in a future release.

Revision History

RevDateChange
02026-09-13First issue — Release 1
Ask the SRT Engineering Assistant

Ask how to apply this tool to your specific situation.

Need SRT to Apply This Directly?

Request a technical assessment — SRT's engineering team can apply this methodology to your project today.