Industry
Rail Transit
Discipline
HVAC & Industrial Ventilation Engineering
Scope
Design, Calculation & Fabrication
Project Type
Industrial Ventilation System

Project Overview

This project is the engineering of a ventilation system for a Train Painting Booth — a 33m(L) × 6m(W) × 6.5m(H) facility designed to manually paint LRV (Light Rail Vehicle) car bodies, with train sets up to 28 meters long (2 car bodies). The engineering challenge wasn't just building an enclosure, but managing three distinct airflows (fresh air, hot air, exhaust air) in balance across that large enclosed volume, while maintaining paint quality and operator safety.

Client requirements included a one-way painting process (train pushed in and pulled out by shunter), use of a high-pressure electrostatic aircoat system, and compliance with safe working conditions in a potentially hazardous area. The system objective was one integrated ventilation chain — not standalone HVAC components.

Client Challenges

High-temperature control for paint curing (up to 150°C design)

Paint overspray and air contamination from a high-pressure electrostatic system

Uniform airflow across a 33-meter-long booth

Operator safety in a high-static-risk work area (electrostatic spray)

Environmental compliance — exhaust air must pass layered filtration before release

Maintenance accessibility across a large, multi-subsystem installation

Engineering Assessment

SRT's team conducted a site assessment (booth positioned outside the main shop building), a process study (one-way painting direction, electrostatic aircoat system characteristics), airflow analysis (balancing fresh air supply, hot air circulation, and exhaust across the booth's volume), equipment layout review (AHU room, heating box, and filtering chambers positioned around the booth), utility review (water circulation, compressed air for spray guns, and total system electrical load), maintenance accessibility (access doors, inspection points), and structural consideration (steel beam structure for the AHU room, insulated chamber construction).

Side view general arrangement of the train painting booth ventilation system, showing fresh air supply, hot air supply/return, and exhaust air paths
General Arrangement — side view of the ventilation system, showing fresh air supply, hot air supply/return, and exhaust air paths.

Engineering Solution

Fresh Air Supply

Fresh air is supplied through a single Air Handling Unit (AHU) sized 8×3.5×3.5m with a steel-beam support structure. Air passes through three filtration stages: a pre-filter SUS wire mesh (insect prevention), a second-stage EU-3 fixed envelope bag filter, and a third-stage EU-5 fixed envelope bag filter — reaching 95% filtration efficiency. A centrifugal supply fan rated at 180,000 m³/hr is driven by a 55kW high-efficiency motor (IP54), with air pressure monitored via a Magnehelic-type differential pressure gauge.

Hot Air Supply

Hot air for the paint curing process is supplied from a batch-oven type heating box (3.6×2×3m), constructed of galvanized plate with rock wool insulation (density 80) between the inner and outer walls. The heat source is a fine heater rated at 180kW. Design temperature is set at 150°C with an operating temperature of 120°C — explicitly noted in the engineering documentation as a value requiring reconfirmation against the actual paint specification, reflecting evidence-based engineering discipline rather than assumption.

Engineering note: the operating temperature value is flagged in the documentation as "needing confirmation from the paint specification" — good engineering practice records assumptions explicitly rather than treating them as final without verification.

Hot air circulation is driven by a centrifugal fan rated at 2,500 m³/min with a 20kW motor (IP54), distributed through 1,800×1,000mm galvanized ducting at a design velocity of 1-3 m/s.

Hot Air Return

The hot air return path brings air from inside the booth back to the heating box for reheating, rather than discharging the entire heated air volume each cycle — an approach that reduces heating energy load compared to a once-through system.

Exhaust Air System

The exhaust system uses a fan rated at 55kW, distributed through 1,800×1,000mm galvanized ducting. Before release to atmosphere, exhaust air passes through a silencer and an acoustic absorbent chamber for noise control, consistent with the layered filtration (water spray elimination + air scrubber) on the booth's filtering chamber side.

Airflow Control

Volume dampers and manual dampers are placed along the fresh air and exhaust paths to balance air distribution across three distinct zones of the 33-meter booth — rather than relying on a single supply/exhaust point for a space that large.

Noise Reduction

A silencer and acoustic absorbent chamber are installed on the exhaust path, with the AHU's own chamber using glass wool insulation over 1.5mm galvanized construction — acoustic treatment applied at two separate points, not just a single muffler at the end of the system.

Utility Integration

A water circulation system (2 pump units at 180 m³/hr, 22kW) supports overspray elimination at the filtering chamber. The system's overall electrical load is calculated and explicitly documented — total connected power of approximately 405kW, with a 20% safety margin bringing the design supply capacity to 450kW on the main 380V three-phase electrical supply.

Maintenance Access

Booth access includes an automatic weatherproof sliding door for primary access, plus two separate swing doors for personnel access — separating vehicle access from routine maintenance access. Check points along the exhaust ducting allow inspection without dismantling the entire duct run.

Engineering Design Highlights

Custom ventilation design for a 33m booth accommodating a 28m LRV

Airflow engineering — three airflows (fresh/hot/exhaust) balanced across zones

HVAC integration — AHU, heating box, and exhaust as one coordinated system

Acoustic engineering — silencer and acoustic absorbent chamber on the exhaust path

Multi-stage filtration — 95% efficiency via 3-stage air filtering + 2-stage water elimination

Structural support design — steel beam structure for the AHU room

Fabrication engineering — galvanized/mild steel construction across all chambers

Installation engineering — separated vehicle and personnel access paths

Commissioning support — covered within the technical specification package scope

Engineering Workflow

Client Requirement Site Assessment Engineering Calculation Concept Design General Arrangement Drawing Detail Engineering Fabrication Installation Testing Airflow Balancing Commissioning

Technical Scope

ScopeDemonstrated in This Project
Mechanical EngineeringYes
HVAC EngineeringYes
Industrial VentilationYes
FabricationRepresented in the specification package scope
InstallationRepresented in the specification package scope
TestingRepresented in the specification package scope
CommissioningRepresented in the specification package scope
DocumentationYes — technical specification and structured capacity calculation package

Engineering Value Delivered

Engineering Evidence

Engineering documentation supporting this project.

General arrangement drawing
General Arrangement Drawing

Technologies Used

Mechanical Engineering HVAC Industrial Ventilation CAD Engineering Steel Fabrication Commissioning
← Back to Case Studies